Eps Class 12 Chapter 8 Objective
12th Entrepreneurship Chapter 8 Objective : Here you can find class 12th eps Objective questions for board exam 2022. concept of FORMULATION OF PROJECT REPORT AND PROJECT APPRAISAL objective questions is very important for board exam 2022. eps class 12 chapter 8 objective question answer.
FORMULATION OF PROJECT REPORT AND PROJECT APPRAISAL
- Pay – back period deals with :
( a ) Period required for profit earning process
( b ) Period required for cost of investment recovery
( c ) Period required for fixed cost recovery
( d ) None of the above
Ans . ( b ) Period required for cost of investment recovery
- Project report is a summary of :
( a ) Facts
( b ) Informations
( c ) Analysis
( d ) All of these
Ans . ( d ) All of these
- In project identification is needed : .
( a ) Experience
( b ) Use of Mind
(c) Both Experience and Use of Mind
(d) None of these
Ans . (c) Both Experience and Use of Mind
- Aspects of project evaluation is :
(a) Technical Evaluation
(b) Financial Evaluation
(C) Managerial Evaluation
(d) All of these Part
Ans . (d) All of these Part
- Money spent on the preparation of project is :
( a ) Investment
( b ) Expenditure
( c ) Wastage
( d ) None of these
Ans . ( a ) Investment
- Project is prepared :
( a ) By Promoters
( b ) By Managers
( c ) By Entrepreneurs
( d ) By all these
Ans . ( d ) By all these
- DPR is a :
( a ) Working Plan
( b ) Action Plan
( c ) Implementation Plan
( d ) None of the above
Ans . ( b ) Action Plan
- Input analysis deals with :
( a ) Funding requirements
( b ) Material requirements
( c ) Labor requirements
( d ) Resource requirements
Ans . ( d ) Resource requirements
- Techno – economic analysis deals with identification of the :
( a ) Supply potential
( b ) Demand potential
( c ) Export Potential
( d ) Import Potential
Ans . ( b ) Demand potential
- Core competency is related with ……… :
( a ) Intrinsic value addition
( b ) External value addition
( c ) Both
( d ) None of these
Ans . ( a ) Intrinsic value addition
- The purpose of project formulations is to determine the …….
( a ) Major impact of the proposed project
( b ) Total impact of the project
( c ) Both
( d ) None of these
Ans . ( b ) Total impact of the project
- Project formulation relates to ……..
( a ) Second stage of project cycle
( b ) Fourth stage of project cycle
( c ) Both
( d ) None of these
Ans . ( a ) Second stage of project cycle